Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Resubmit Plans: The applicant resubmits plans.

  • Scout API Validation: The resubmitted plans are sent to the Scout API for validation.

  • Validation Results:

    • If the application fails validation again, corrections deliverables are returned to the applicant resubmits plans.

    • If the application passes validation, it moves to the Permit System for further processing.

...

  • Generate Approval Deliverables: Approval deliverables are generated for the approved plansprovided to the Applicant.

2. EPR Scout API

New Application/Record/Permit:

  • Validate Application/Plans: The Scout API validates the submitted application/plans.

  • Validation Results:

    • If the application passes validation, it moves to the Permit System.

    • If the documents fail validation, the reason for failure is returned to the Applicant Portal.

Plans Resubmitted:

  • Validate Resubmitted Plans: The Scout API validates the resubmitted plans.

  • Validation Results:

    Confirm Approval Deliverables: The Scout API confirms the approval deliverables
    • If the application passes validation, it moves to the Permit System.

Approved Plans:

    • If the documents fail validation, the reason for failure is returned to the Applicant Portal.

3. Permit System

New Application/Record/Permit:

  • Check Plan Review Requirement: The system checks if the application requires a plan review.

    • If no plan review is required, no integration occurs.

    • If a plan review is required, a project is created and moves to the Intake Process.

Plans Resubmitted:

  • Documents Checked for Resubmittals: Permitting Solution validates receiving all required documents for the next plan review cycle.

Review Complete:

  • Process Corrections Deliverables: The system processes corrections deliverables if corrections are needed.

...

  • Process Approved Plans: The system processes the approved plans and creates approval approved deliverables.

4. Intake - EPR

...

  • Upload Documents and Complete Intake: Documents are uploaded, and intake is completed.

Plans Resubmitted:

  1. Create Corrections Deliverables: Corrections deliverables are created if corrections are needed and returned to the permitting solution.

5. Reviewer - EPR

New Application/Record/Permit:

  • Complete Reviews: Reviews are completed.

    Review Approval:

  • If all reviews are approved, approved deliverables are created and moved to the Permit System.

  • If reviews are not approved, corrections deliverables are created and sent back for resubmission

    .

Integration Points

  • Applicant Portal to EPR Scout API

    • Integration Point: Application/Plans submission and validation.

    • Purpose: To ensure submitted plans meet validation criteria.

  • Permit System to EPR

    • Integration Point: Plan review requirement check and project creation.

    • Purpose: To determine if the application requires a plan review and to create a project if necessary.

  • Reviewer - EPR to Permit System

    • Integration Point: Document/Task Statuses

    • Purpose: Communication of plan review program.

  • Permit Staff - EPR to Permit System

    • Integration Point: Review completion and deliverable creation.

    • Purpose: Return deliverables to the applicant upon completion of the review cycle.

...

Filter by label (Content by label)
page
showLabelsfalse
max5
spacescom.atlassian.confluence.content.render.xhtml.model.resource.identifiers.SpaceResourceIdentifier@10c5c
maxCheckboxfalse
showSpacefalse
sortmodified
showSpacetypefalsepage
reversetruetype
labelskb-how-to-article