Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

User roles cannot be renamed, however, adjusting the permissions for each user roles is supported.


User RoleDescription
Admin
Responsible for user accounts, permissions and configurationReviewerThis individual conducts plan reviews and may be granted permissions to generate correction
reports and prepare deliverable packages

The Admin role is mainly tasked with assisting in the initial configuration of the EPR portal and with updating portal configurations as needed.

Some of the most significant Admin abilities include managing:

  • User accounts
  • Assignment distribution workflows
  • The standard comment library
  • Corrections Report Letter templates
  • Stamps and user stamp access
  • Email notification templates
  • Drop-down list values

The Admin role can also perform the functions of every other user role in EPR, including project creation, assignment intake, plan review, and packaging deliverable back to applicants.

Project Coordinator

This user typically coordinates many projects for one or more Managers.

This user may also be granted permissions to manage configurations, perform Intake and
prepare deliverable packages.

Project ManagerThis user typically manages their own Projects.Group ManagerThis user manages plan reviewers in his Group(s) and may be granted permissions
to edit/delete markups for users in his Group(s).

The Project Coordinator is usually reserved for intake staff/permit technicians.

The main responsibilities for these users are to:

  • Create plan review tasks (“assignments”) for reviewers
  • Update assignment tasks or reassign, as needed.
  • Prepare corrections report letters (typically)
  • Prepare deliverable packages of marked-up or approved plans to send back to applicants at the end of a review cycle.

When all review assignments have been given an approved, rejected, or canceled status, Project Coordinators will be notified so they can prepare a Corrections Report letter with all reviewer feedback and then package files to return to the applicant, either through email or, more commonly, through check-in to an integrated portal.

Project Manager

The Project Manager is the highest level of ‘Reviewer-type’ role but has the added ability to edit and delete markups created by other reviewers within the project he or she is managing.

A Project Manager cannot edit or delete markups for another Project unless they also manage that Project.

Group Manager

The Group Manager functions as an elevated ‘Reviewer-type’ role but has the added ability to edit and delete markups created by other reviewers within his or her Group (by default, a reviewer can only edit his or her own markup activity).

A Group Manager cannot edit or delete markups for another Group unless they also belong to the other Group.

Reviewer

The Reviewer’s main responsibilities are to:

  • Review and markup plans submitted by an applicant
  • Provide feedback through comments and/or stamp approved plans as appropriate.
  • Evaluate the submittal by setting an assignment Status (Approved, Resubmittal Required, etc.)

Reviewers belong to one or more Groups (think of these as Departments or Sub-departments) and are responsible for completing plan review tasks (“assignments”) made for their Group. In some cases, especially for larger agencies, assignments are made for a specific named Reviewer within a Group. Although other users are still able to access the assignment, the named Reviewer is expected to complete the review assignment task.

At the end of a review cycle, the reviewer must provide either an approval, rejection, or other status for the assigned plans and, if appropriate, may stamp plans as well. Reviewers can also create Corrections Report letters, if desired. The Reviewer role is not configured to perform intake of plans or prepare deliverable packages to send back to an applicant – for this functionality, see Project Coordinator.

Contributor

A licensed user who has been granted

permissions

access to view and respond to comments made by the Reviewers in an existing project.

The contributor can view projects where they have been added to the project team (they are a "team member"). For these projects, they can view comments and add responses to any that have 'response enabled' set by the reviewer. They cannot respond if response is not enabled, nor can they create new comments or markup plans.


Info

Contributors are prevented from functioning as Plan Reviewers and cannot be granted permissions to the Review page.

...